SEWP VI Program Tracker
The running list on this page is the Inspired Solutions desk copy. The live board is monday.com board 18423435750, SEWP VI Program Tracker. Update the board when a row moves. Do not treat this HTML as the system of record after someone edits monday.com.
How to read the list
- Internal dates are Inspired Solutions targets. They are not NASA due dates unless the row says NASA.
- If the path is not posted, nothing transmits. Rick sends NASA email.
- Awarded. Not effective. Not active. Do not quote. Do not take orders.
- Onboarding work for Exhibit 4, C-SCRM, and the company logo goes on NASA case 1235177, not CHOP.
This week (week of 25 August 2026)
CHOP is WAITING ON NASA. NASA confirms when the account emails go to Rick (PM) and Isabella (DPM) only. The 24 Aug PM/DPM reply does not auto-trigger CHOP. Do not self-register. Do not use Forgot Password. After both register, then set contacts, email reports, and PM/DPM designations. Michael tests after both are in. Test is not live quoting.
| Task | Lane | Status | Note |
|---|---|---|---|
| Exhibit 4 ASAP | Fatima / Desi | In progress | Submit on case 1235177, not CHOP. Size as of proposal. Yes only on applicable NAICS. |
| C-SCRM / Attachment J or ISO 20243 | Rick PM | In progress | Due in onboarding on case 1235177. Rick owns Q1.6. One company-level package. Do not mix with AbilityOne. |
| Company PNG logo, min 300k | Rick PM | Open | Upload on case 1235177. Company logo, not the NASA ContractHolder mark. |
| One SEWP webpage + one ordering guide | Rick PM | In progress | One page and one guide cover both Cat A 80TECH26D1138 and Cat C 80TECH26D0142. Do not publish to inspired-us.com until ready. |
Waiting or hold as of 27 August 2026
| Item | Owner | Status | Note |
|---|---|---|---|
| CHOP registration | Rick, Isabella | Wait NASA | WAITING ON NASA. They confirm when they send the links to PM and DPM only. Do not self-register. Do not use Forgot Password. |
| CHOP contacts / email reports / designations | Rick, Isabella | Hold | After both Rick and Isabella register. Not before. |
| Technology Refreshment submit | April | Wait NASA | No TRs until NASA says (Sept). Official TR Headers xlsx posted 26 Aug. Prepare the file. Do not submit. |
| AbilityOne | Karen | Hold | Later. Standby. Nothing transmits until NASA says. Do not mix with C-SCRM. |
| Category C rates versus GSA | Fatima Desi Almanzar | Blocked | Do not publish rates. |
| Jim Griffin letter | Rick | Hold | Rick sends NASA email. Do not freelance a note to the Contracting Officer. |
Tasks 1 to 50
Status as of 27 August 2026. Both contracts are executed. Category A 80TECH26D1138 (award 24 June 2026). Category C 80TECH26D0142 (award 5 July 2026). Case 1235177 onboarding email 24 August started the 60-day clock. Active when the checklist is complete except the credit card fee. RFQs and orders 1 November 2026. Expected effective 1 November 2026.
| # | Task | Owner | Status | When |
|---|---|---|---|---|
| 1 | CHOP PM/DPM registration WAITING ON NASA. NASA confirms when the account emails go to Rick and Isabella only. Do not self-register. Do not use Forgot Password. After both register, then set contacts, email reports, and PM/DPM designations. |
Rick, Isabella | Wait NASA | When NASA sends the links |
| 2 | CHOP email roster Settled. Rick PM and Isabella DPM on inspired-us.com. No aliases. Wait for NASA emails. After both are in, Michael tests. Test is not live quoting. |
Rick, Isabella, Michael | Done | Roster settled. Wait NASA emails |
| 3 | CHOP acceptance test, Category A and Category C After both PM and DPM register. One CHOP identity per UEI. Test both entitlements. Test, not live quoting. |
Michael Nwokeabia | Hold | After both register |
| 4 | Daily NASA SEWP VI page check 27 Aug 5:41 PM ET: no new files since the 26 Aug TR Headers drop. CHUM 082126 is live on the NASA SEWP VI page. Auxiliary 081226 V2 still current. |
April Moshos, this desk | Recurring | Daily |
| 5 | Onboarding checklist on case 1235177 Clock started 24 Aug. Active when the checklist is complete except the credit card fee. Submit Exhibit 4, C-SCRM, and the PNG logo on the case. Full recap on monday.com item 12917093540. |
Rick, April | In progress | 60-day clock from 24 Aug 2026 |
| 6 | 27 Aug CHRM office hours Notes posted on monday.com item 12917093540. PM/DPM reply does not auto-trigger CHOP. Exhibit 4, C-SCRM, and logo go on case 1235177. One webpage + one guide for both cats. |
Program | Done | 27 Aug 2026 |
| 7 | C-SCRM / Attachment J or ISO 20243 on case 1235177 Due in onboarding. One company-level package per UEI. Do not mix with AbilityOne. Do not submit from a hallway version of the form. |
Rick, Program | In progress | Onboarding, case 1235177 |
| 8 | Q1.6 Rick decision Rick owns Q1.6 (NIST 800-171, 14 families). Do not claim all 14 families without evidence. Now part of the onboarding package, not an internal-only hold. |
Rick | In progress | With C-SCRM on 1235177 |
| 9 | AbilityOne standby Later. Not part of the current case 1235177 push. Karen standby. Nothing transmits until NASA says so. Do not combine with C-SCRM. |
Karen McCleary | Hold | Wait NASA |
| 10 | NIB contact Dean Simmons for Category A AbilityOne Products path. Standby on transmit. |
Karen McCleary | Hold | When NASA opens AbilityOne |
| 11 | SourceAmerica for Category C AbilityOne Services path. Same standby rule. Nothing transmits until NASA says so. |
Karen McCleary | Hold | When NASA opens AbilityOne |
| 12 | One submission per contract holder for C-SCRM, AbilityOne, and ISO Do not send two. Do not combine the three packages. |
Program | Open | When NASA posts each path |
| 13 | Exhibit 4 on case 1235177, ASAP 27 Aug listserv: submit on case 1235177, not CHOP. Size as of proposal. Yes only on applicable NAICS. Official form 071626. Do not use the RFP version. |
Fatima Desi Almanzar | In progress | ASAP this week |
| 14 | SAM / banking match Names, banking, and SAM have to match before NASA will treat the holder as ready. |
Fatima Desi Almanzar | In progress | Open now |
| 15 | Catalog / TR desk No TRs until NASA says (Sept). Official TR Headers xlsx posted 26 Aug. Prepare the 1,896 Category A rows against that template. 1,500 searchable CLINs by 1 October is still an internal target. Do not submit. |
April Moshos | In progress | Prepare now. Submit when NASA says |
| 16 | Rebuild providers. No carryover from the proposal Providers must be set up before offerings. Database of Record rule still applies. FedRAMP: sign up later on the providers page or Inspired Solutions will not show as a seller. |
April Moshos | Open | Before catalog load |
| 17 | OEM part numbers and UNSPSC on catalog rows OEM part number required on product CLINs. UNSPSC on every CLIN, including Category C services and LCATs. Class or commodity level. Predominant purpose. Allowed versus limited. One CLIN error fails the whole TR. |
April Moshos | Open | With catalog build |
| 18 | Remove Dell GOLD Do not carry GOLD rows into the SEWP VI catalog. |
April Moshos | Open | With catalog build |
| 19 | Category C LCAT plan Zero Category C CLINs on contract today. Plan the labor categories. Do not publish rates. |
Fatima Desi Almanzar, Program | Open | Before rates publish |
| 20 | Category C rates versus GSA Internal blocked item. Do not publish rates. Do not put rates on a customer page. |
Fatima Desi Almanzar | Blocked | Hold |
| 21 | GSA price ceiling in the quote desk Build the ceiling into the desk before anyone can quote. Still no quotes now. |
Fatima Desi Almanzar, quote desk | Open | Before any quote path |
| 22 | One required public SEWP webpage for both cats 27 Aug CHRM: one webpage even with two cats. Cat A 80TECH26D1138 and Cat C 80TECH26D0142 share one page and one ordering guide. Contract-required unique SEWP-only URL. Not this internal desk. Do not publish to inspired-us.com until ready. Internal target 25 September. |
Rick | In progress | Internal target 25 Sep 2026 |
| 23 | Kickoff travel, Louisville, already registered Confirmation 72558164. Louisville, KY, 2 to 4 November. Attend all 3 days. 2 people per company. Late Monday is OK. Hotel and conference block links are still not on the NASA page. NASA does not pay travel. |
Rick, Isabella | Done | Registered. Attend 2 to 4 Nov 2026 |
| 24 | Fee factor 0.0033885 in quoting and finance Fee is 0.34 percent and is never a line item. Quarterly on invoiced and collected. No customer number yet (new Category A and C holder). Pay.gov later: HQ / SEWP Fees / 800000001. The $24,999 cap is CH-to-SEWP only. PM is finance POC. |
Quote desk | Open | Before any quote path |
| 25 | Credit card / GPC / surcharge Not required for active-CH status. Still declare actual processor cost later. Know the rule before a buyer asks. Still no orders. |
Fatima Desi Almanzar | Open | Before any quote path |
| 26 | SDVOSB recertification Keep the recert on the calendar. Do not let it slip into the first ordering year. |
Program | Open | Dec 2026 |
| 27 | ISO 9001, ride current cert One ISO submission per holder when NASA posts the path. Do not combine with AbilityOne or C-SCRM. ISO 20243 is an alternate path for the C-SCRM onboarding item, not this ISO 9001 row. |
Karen McCleary | Open | When NASA posts ISO path |
| 28 | Mirror public docs Keep an internal copy of what NASA has posted, before the 30 September cutoff. |
Program | Open | Before 30 Sep 2026 |
| 29 | NASA comms to PM/DPM PM/DPM reply sent 24 Aug 8:47 PM ET on case 1235177. Jim Griffin letter is HOLD. Rick sends NASA email. Do not freelance from a sales mailbox. Do not send 1449 change requests or novation now. |
Rick | In progress | By 31 Oct 2026 |
| 30 | Watch posted recordings Deep Dive Days 1 to 5 and the 17 Aug Q&A are posted. 20 Aug office hours recording is posted. 27 Aug CHRM office hours notes are on monday.com item 12917093540. |
Rick, Program | Done | Posted |
| 31 | Auxiliary V2 is Q&A of record Posted 12 August 2026. Still current as of 27 August. Use it when a hallway version disagrees. |
Program | Done | Posted 12 Aug 2026 |
| 32 | CHUM 082126 is live NASA posted the Contract Holder User Manual 082126 on the SEWP VI page. Use the current posted file. Do not use a delisted older copy. |
All | Done | Live on the NASA SEWP VI page |
| 33 | Quote only when both contracts are effective AND active Expected effective 1 November 2026 is not the go-active date. Active is checklist complete except credit card fee. Effective is not active. Still do not quote. RFQs and orders 1 Nov. |
Quote desk | Hold | After effective and ACTIVE |
| 34 | Definition of Ready before any quote Write the ready gate before the first RFQ. Catalog, Control Number, fee, and eligibility have to be in that gate. |
Quote desk, Rick | Open | Before first quote |
| 35 | Control Number and CLIN checker on every quote path No Control Number, no quote and no fulfill. CLIN checker at quote AND at order if the RFQ is missing or does not match. CLIN list must match the order total. The path is not open yet. |
Quote desk | Open | When quoting opens |
| 36 | Storefront / BPA awareness Know that storefronts and BPAs will exist. Do not promise a storefront date. |
Sales, inside sales | Open | Before hard outreach |
| 37 | Accessibility storefront prep Prep only. Wait for NASA to post the storefront path. |
Program | Open | When NASA posts storefront path |
| 38 | WWT competitive posture World Wide Technology holds Category A and Category B. Inspired Solutions holds A and C. WWT is a partner. Not a betrayal. Not eligible on a small-business set-aside. |
Sales | Open | Ongoing |
| 39 | Parser / email templates when NASA posts Do not invent a parser spec. No API. Wait for NASA. |
Michael Nwokeabia, quote desk | Wait NASA | When NASA posts |
| 40 | Dry-run quote path in October October is browse-only. Internal dry-run only. No customer quotes. No RFQs until the effective date. |
Quote desk, Rick | Open | October 2026 |
| 41 | Dormancy and delivery rating Working brief: a quote quarterly, one order per year, attend required meetings, answer NASA. Delivery rating is customer-visible. Keep CHOP order status current. Delayed is a closed dropdown. OEM late is not a reason. Do not tell a buyer we must take their order to stay active. |
Program | Open | After go-live, brief before 1 Nov |
| 42 | Monthly progress reporting Report when NASA posts the path. Do not invent a format. |
Rick, Isabella | Recurring | After NASA posts the report path |
| 43 | FAR 52.219-14 Limitations on subcontracting. Brief it before the first Category C order. |
Program | Open | Before first Category C order |
| 44 | OCI review per task order Organizational conflict of interest review is per task order, when orders exist. |
Program | Recurring | Per task order |
| 45 | Category C order limits Know the limits before the first services order. Zero CLINs today. Still no orders. |
Program, quote desk | Open | Before first Category C order |
| 46 | Provider public-facing review Customers can see Inspired Solutions on the customer-facing SEWP site on 1 October. Browse-only. Still no quotes. |
April Moshos, Rick | Open | Before 1 Oct 2026 |
| 47 | One ordering guide for both cats 27 Aug CHRM: one guide covers Cat A 80TECH26D1138 and Cat C 80TECH26D0142. Use the NASA example. Pair it with the one SEWP webpage. Do not publish to inspired-us.com until ready. |
Program | In progress | With the one webpage |
| 48 | Recommended LCAT list when NASA posts Wait for NASA. Do not publish an Inspired Solutions LCAT list as if NASA issued it. |
Program | Wait NASA | When NASA posts |
| 49 | Company PNG logo, min 300k, on case 1235177 27 Aug CHRM: upload the Inspired Solutions company logo as PNG, minimum 300k, on case 1235177. Not the NASA ContractHolder mark. One logo for both cats. |
Rick | Open | This week, case 1235177 |
| 50 | Active-status package so both contracts go effective 1 November Clock started 24 Aug on case 1235177. Active when the checklist is complete except the credit card fee. RFQs and orders 1 Nov. Effective is not active. Do not quote until both are effective and active. |
Rick, Isabella, Program | In progress | Expected effective 1 Nov 2026 |
27 Aug CHRM office hours and last few NASA facts
Folded into the 1 to 50 list above. Do not renumber. Read the updated rows, then this reminder:
- Case 1235177 onboarding email 24 Aug. Rick sent PM/DPM 24 Aug 8:47 PM ET. Do not resend.
- PM/DPM reply does not auto-trigger CHOP. WAITING ON NASA for the links. Links go to PM and DPM only. Do not self-register. Do not use Forgot Password.
- 60-day clock started 24 Aug. Active when the checklist is complete except the credit card fee. RFQs and orders 1 Nov.
- Exhibit 4 ASAP on case 1235177. Size as of proposal. Yes only on applicable NAICS. Fatima / Desi.
- C-SCRM / Attachment J or ISO 20243 due in onboarding on 1235177. Rick owns Q1.6.
- PNG logo min 300k on 1235177. Company logo.
- One SEWP webpage + one ordering guide for both Cat A 80TECH26D1138 and Cat C 80TECH26D0142. Do not publish to inspired-us.com until ready.
- AbilityOne later. Karen standby.
- No TRs until NASA says (Sept). TR Headers xlsx posted 26 Aug. April prepares only.
- Kickoff already registered, confirmation 72558164. Attend all 3 days, 2 people per company. Late Monday is OK.
- CHUM 082126 is live on the NASA SEWP VI page.
Who owns what
One owner per lane. Escalate to Rick, then Isabella. Do not invent a second owner because someone is out.
NASA Contracting Officer is Jim Griffin, sewp6@sewp.nasa.gov. Rick sends NASA email.
Internal draft. 27 August 2026. Not for customers. Not for quotes. Home · This week · Quoting